F06A/1613
GRANT PERM. CONSEQUENT TO OUTLINE PERM.
28-Mar-2007
If a decision has been made, then listed below are the conditions and reasons attached with the decision of Fingal County Council. The category of decision made, determines what is displayed under the type column:
- Conditions are associated with grants
- Reasons are given for refusals
- Directives are items requested under Additional Information
- Informatives are items requested under clarification of Additional Information
- Notes are reasons for invalidating a planning application
In some cases, a combination of conditions, reasons, directives and informatives are used with regard to split decisions i.e. grant permission and refuse permission.
N.B. In the event of an appeal, any decision by An Bord Pleanala will supercede the above, the details of which (from 2002 onwards) can be found by following the path to the website under the Appeal tab.
| Type |
Description |
| Condition
|
The development to be carried out in its entirety in accordance with the plans, particulars, specifications, and information lodged with the application, as amended by additional information received on 5th March 2007, save as may be required by the other conditions attached hereto.
REASON: To ensure that the development shall be in accordance with the permission and that effective control be maintained.
|
| Condition
|
Prior to the commencement of development the applicant shall submit for the agreement of the Planning Authority an acceptable front elevation of the proposed vehicular entrance and front boundary.
REASON: In the interest of visual amenity.
|
| Condition
|
The developer shall pay the sum of €35,760 (updated at date of commencement of development, in accordance with changes in the Tender Price Index) to the planning authority as a contribution towards expenditure that was/or that is proposed to be incurred by the planning authority in respect of public infrastructure and facilities benefiting development in the area of the Authority, as provided for in the Contribution Scheme for Fingal County made by the council. The phasing of payments and the giving of security to ensure payment shall be agreed in writing with the planning authority prior to the commencement of development.
REASON: It is considered reasonable that the payment of a contribution be required in respect of the public infrastructure and facilities benefiting development in the area of the planning authority and that is provided, or that is intended will be provided, by or on behalf of the Local Authority.
|
| Condition
|
All necessary measures including the provision of wheel wash facilities shall be taken by the contractor to prevent the spillage or deposit of clay, rubble, or other debris on adjoining roads during the course of the works.
REASON: To protect the amenities of the area.
|
| Condition
|
The proposed house shall be used as a single dwelling unit.
REASON: To prevent unauthorised development.
|
| Condition
|
The water supply and drainage infrastructure, including the disposal of surface water, shall comply with the technical requirements of the Planning Authority in particular:
Foul Sewer
i) No foul drainage is to discharge into the surface water system under any circumstances.
ii) The foul drainage must be in compliance with the ‘Regional Code of Practice for Drainage Works Version 6.0’ FCC April 2006.
Surface Water
i) No surface water/rainwater is to discharge into the foul sewer system under any circumstances
ii) Soakways must comply with BRE Digest 365 and be at least 5m from the proposed dwelling.
Water Supply
i) To assist in monitoring the level of service, at each stopcock the applicant is to provide a boundary box to a design approved by the Water Division, Fingal County Council.
ii) The following works shall be carried out by Fingal County Council Water Division at the applicant's prior expense:
a. the connection to the public watermain
b. the testing, cleansing and sterilisation of all new mains
c. the provision of tappings to serve individual properties
iii) To ensure a continuation of water supply, the applicant is to provide for 24 hour water storage
iv) All water fittings and installations shall incorporate best current practices in water conservation.
REASON: In the interests of public health and in order to ensure adequate drainage provision.
|
| Condition
|
The following requirements of the Transportation Department, Fingal County Council shall be strictly adhered to:
i) The front boundary of site to be set back 5.5 metres from the centreline of the existing carriageway (Healys Lane). The strip between edge of carriageway and boundary to be levelled and grassed to County Council Standards. This is to allow for future road widening and the provision of a 1.5m footpath and grass verge.
ii) The northern boundary along Whitestown Road, to be set back to a line to be agreed with the Transportation Department to allow for future road improvements and provision of a footpath and grass verge. The area between existing carriageway and new boundary to be finished to the requirements of the Area Engineer, Road Maintenance.
iii) The vehicular access to the site to be located at the south-eastern end of the site (off Healy`s Lane).
iv) Entrance gate to be recessed a minimum of 5.0m from carriageway edge with wing walls/fence/hedgerow splayed at 45°.
v) No development of any form including planting, fences or wing walls shall exceed a height of 0.9 metres within the area required to provide visibility from the site entrance point.
vi) All storm water to be disposed of to soakpits or natural watercourse within the site and not to discharge onto the public road.
vii) Parking for two cars to be provided within the curtilage of the site with an adequate turning area.
viii) All underground or overhead services and poles to be relocated, as may be necessary, to a suitable location adjacent to the new boundary at the developer’s expense.
ix) All works to be carried out at the applicants' expense and to the requirements of the Transportation Department of Fingal County Council.
REASON: In the interest of traffic safety.
|
| Condition
|
Any gates shall not open across a public footpath.
REASON: In the interests of visual amenity and pedestrian safety.
|
| Condition
|
All public services to the proposed development, including electrical, telephone cables and equipment shall be located underground throughout the entire site.
REASON: In the interest of amenity.
|
| Condition
|
All bathroom windows shall be fitted and permanently maintained with obscure glass.
REASON: In the interest of residential amenity.
|